LRT Operation Trial will Stay On Schedule
access_time January 24 2018 11:04 AM remove_red_eye 1163
Reported by Oki Akbar | Translated by Nugroho Adibrata
Reported by Oki Akbar | Translated by Nugroho Adibrata
PT Jakarta Propertindo (Jakpro) assured, the collapsed box girder incident on Light Rail Transit (LRT) yesterday will not disturb its operation trial in May.
That's the estimate with all the situations they face
PT Jakpro President Director, Satya Heragandhi said PT Wijaya Karya (Wika), the contractor of LRT has re-scheduled the construction. At least, it will take one up to one and half month to repair damaged construction.
Collapsed LRT Box Girder will Not Hamper Development Plan"That's the estimate with all the situations they face. Even, this morning, they have started production of replacing girder box that fell," he expressed, at City Council building, Tuesday (1/23).
His party also has got a report about LRT project rescheduling that saying target of box girder repair will be changed.
"So the box girder P 28 and 29 that should be in the mid will be executed at the end. Thus the project can take place parallel thus all can be done on time," he stated.